When does a new Sprint start?

Enhance your Scrum Product Owner skills for the PSPO II Exam with detailed questions and explanations. Study effectively and boost your chances of success!

Multiple Choice

When does a new Sprint start?

Explanation:
A new Sprint starts immediately after the previous Sprint ends. Sprints are timeboxed iterations that create a regular cadence, and the next Sprint begins with Sprint Planning to select the work for the upcoming increment. This start does not wait for backlog refinement to finish, and it does not require stakeholder approval—backlog refinement is an ongoing activity, and stakeholder consent isn’t a gating factor for starting the next Sprint.

A new Sprint starts immediately after the previous Sprint ends. Sprints are timeboxed iterations that create a regular cadence, and the next Sprint begins with Sprint Planning to select the work for the upcoming increment. This start does not wait for backlog refinement to finish, and it does not require stakeholder approval—backlog refinement is an ongoing activity, and stakeholder consent isn’t a gating factor for starting the next Sprint.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy